Mark a job processed
DM
Failed job notices that are assigned to you or a group to which you belong remain in your inbox until they are processed. You can only work with an add request that is assigned to you. To work with a change request assigned to your group, you must first re-assign it to yourself. Processing a failed job notice removes it from the inbox, where it requires no further action.
- In the inbox, click on a failed job notice.
- At the top right of the notice, click Mark Processed.
- In the Mark Issue as Processed dialog box, type a resolution note
Comments that can be used by data stewards to explain the rejection or approval of a data change request..
- Select the Go to next task checkbox if you want to open the next task after you apply the change.
- Click Apply.
Depending on whether you chose to display the next task, the next task or the inbox appears and displays a message that the task has successfully been applied.